Nahadah 400/132kV GIS Grid-Station Conceptual Study Workshop

Following the Process of Conceptual Study and Preparation of Preliminary Design Report Of 400/132 Kv Nahadah Grid Station and Its Associated LILO Work Project by Monenco Oman, The Same Report Submitted to All Associated Department of Our Omani Client, OETC, To Be Reviewed. Thereafter Monenco As The Client Consultant Invited All The Involved Parties In A “ Workshop” In OETC Office With Presence Of PDO Representatives As End User Of The Project To Introduce The Project And The Path We Have Envisaged For The Design Procedures And Above All To Get Their Comments/Advices Based On Their Points Of View Which Subsequently Would Be Utilized In The Finalization Of The Very Design. Since the Workshop Covered So Many Accepts from Initiating of The Project till End of The Design Stage, OETC Teams Contributed Interestingly and The Client Appreciated Monenco Team for Their Excellent Presentation.